For many OR directors, building a new
operating room suite is a once-in-a-lifetime project. A few have the opportunity more than
once.
Directors often embark on a building project without much expertise in reading
blueprints or working with an architect. But they face a series of decisions that will
govern how well their surgical suite functions for years to come.
In
this article, OR directors who have been involved in
construction projectsin
most cases, more than oneshare their survival tips.
What should be your role as OR director?
Be
involved from the start. "You cant come in after the plans are laid
out. You have to be involved from the beginning," says Pat Kroesch, RN, director of
surgical services at Rush-Copley Medical Center in Aurora, Ill, who has been involved in
two building projects. "You are the one who knows how
the OR works. You are the voice of functionality. You have
to be able to talk to the architect and builder. You almost
have to educate them."
Darlene
Astuto, RN, who has participated in building or expanding
three facilities, comments, "I see my role as representing all of the interestspatients, staff,
and physiciansto the architects so we will get the
facility we want."
Nursings role is keeping the team focused on the needs of the patient, in the
view of Renae Burchiel Battie, RN, MN, CNOR. She is
perioperative service line manager at the University of Washington,
Seattle, which is building a big new ambulatory
pavilion with 11 ORs. For example, one of her values is giving
the family space to meet with the surgeon, not in a big waiting
room but in a more quiet space.
What are your tips for working with the architect and design team?
"We learned early that form must follow function. You must talk first about
the flow of patients, staff, and suppliesthink functionality, then space," says
Dru Beedle, RN, MN, CNOR, CNA, a perioperative nursing consultant and past director of
perioperative services at the University of Colorado Health Sciences Center in Denver,
where she participated in building of a 12-OR inpatient suite and was involved in the
planning the universitys new outpatient pavilion.
If
the architects havent built an
OR before, consider having them visit an OR that works
well to observe for a couple of days, Kroesch suggests.
Educate them about the
sterile field and flow of patients, instruments, and materials.
Have
a knowledgeable person show you how to read architectural
drawings and plans, Battie advises. "Check the plans carefully, and dont be afraid to ask
dumb questions." Have a knowledgeable person
show you how to read the plans. She learned that the actual
location of the surgical lights was not where she
thought it was in the drawings because the symbol for the
lights was offset.
How do you involve physicians? It is so hard to get them to come to meetings.
By any means necessary, directors suggest. Of course, you will include physician
representatives on the design team and encourage them to attend meeting whenever possible.
Says
Astuto, "I cant stress this enough: If you have a strong physician
group, you had better have them at the table. You dont want them feeling they
werent consulted."
Several
managers suggested hanging blow-ups of schematic floor
plans in lounges and hallways. Provide
notepads so staff and physicians can make comments. Be
available for
conversations about the drawings. At the University of Colorado,
department chairs were included on the committee. As
critical issues came up, they were invited to the meetings.
Beedle also attended the surgeons section meetings
to keep them up-to-date.
How should the staff be involved?
The staff has expertise that should be tapped on issues involving the functioning
of the suite, layout of ORs, patient care, and materials handling. For example,
circulating nurses should help decide what supplies will be stored in the ORs, the sterile
core, and the central service department.
If you will have a case cart system, they should help decide which supplies will be
stocked on the case cart and which will be added in the OR. They should help determine how
the OR will be linked to the case cart area.
Dont
forget to involve other key people, such as the risk
manager and infection control
professional. Ask if they foresee problems with the plans.
For example, in one
project, the planners had placed the ultrasonic washer on
the wrong side of the decontamination area.
How
do you keep track of the detailsand
make sure nothing falls through the cracks?
Identify your critical issues for the finished suite, directors suggest. Follow
these issues through each stage of the project to make sure they are addressed. Examples
are location and designation of electrical outlets and negative and positive pressure
flows from the air-handling system.
Insist
on receiving detailed minutes of each meeting with the
architect and contractor. Its
also a good idea to keep your own record of each meeting
and conversation.
"I kept a diary of every meeting, contact, and conversation," says Astuto.
"That way I had a record of what everyone had said and who was supposed to get back
to me. As things were finalized, I highlighted them. "This
was a pain, but I found it helped more than anything else.
A lot of paper comes from the architects, but I felt I
needed my own notes."
Did you build a mock OR? Do you recommend doing this?
A
mock OR is helpful for determining spatial relationships,
such as the location of the door,
cabinets, and ceiling-mounted arms. But it can be pricey,
and it isnt
foolproof.
"We built a mock OR, and we still made mistakes," comments
Beth Suriano, RN, CNOR, director of surgical services
at Jupiter Medical Center in Jupiter, Fla, who was
involved in building a new eight-OR suite. The mock OR, built
in a classroom at a cost of about $3,000, had walls with
Styrofoam plaques to represent outlets, light switches,
and
film boxes. The articulating arms were positioned overhead.
Even so, was hard to anticipate all of the relationships
between doors, wall cabinets, and equipment.
An alternative is to visit other OR suites that are well designed, preferably with
other members of the design team. Other options are computer simulation and the low-tech
method of moving paper pieces around on a floor plan.
What about the finished OR suite are you especially glad you did?
- Planned dedicated equipment space so equipment does not clutter the hallway.
The University of Colorado built a long, narrow room
so equipment could be lined up against both walls. "We traced a footprint of each item, such as microscopes, and
labeled the spaces," says Beedle. At Jupiter Medical Center, equipment is stored in
4-foot alcoves in the ORs 12-foot-wide back hallway.
The alcoves have signs indicating where equipment is
to be parked.
- Organized the sterile core by specialty. "We have signs hanging from the
ceiling so anybody can see the area where they need to look," says Suriano. "We
get a lot of compliments from travelers who say how organized
it is because of the signs."
- Organized the sterile core for case cart assembly. Central
service staff assemble the case carts in the evening.
In the old OR, this work was done by RNs and
surgical techs. The CS staff has been educated about
the OR inventory and computerized pick lists and is
supervised by an "OR core RN."
What do you wish you had done differently?
- When planning cabinets in ORs, consider all specialties that will use the OR.
Will the OR table block access to the cabinets during certain types of cases?
- List all equipment that will be used in each OR to ensure electrical power is
adequate.
- Fight for storage space. There is never enough, and it is always the first item
crossed off the list if more room is needed or the budget is tight.
- Think about the communication system. Think of all the ways in which phone
lines will be used and plan for enough lines. Consider other technologies. Will you use
pagers? If so, will signals penetrate lead-lined walls? Will you use a computerized
patient-tracking system? Is it compatible with the information system you currently have?
- Waste disposal should not be an afterthought. The OR produces more medical
waste than any other department. Build an efficient area to dispose of waste. Plan a dirty
utility room large enough for Dumpster-type containers. Make sure the room is properly
located for your system, for example, not behind the red line. Will you need an elevator
to transport waste? Look at high-tech options, such as self-washing chutes designed for
contaminated waste. This could be a time saver for your staff, but it must be built in to
the design.
- Be aware of room numbering. This may sound trivial. But Beedle learned that
once the rooms were numbered on the drawings, the numbering was keyed to the plumbing,
HVAC, and fire control systems. It was too complicated to change the numbers later even
though they were not in the order she and her team would have chosen.
What do you know now that you wish you had known at the beginning?
- Use your network. Talk to other OR directors who have been through a building
project. Have them look at your plans and give their advice.
- Be assertive. "If you know something is right, dont give up,"
Astuto asserts. "Fight for it. Dont let them
tell you there is not enough money.
"You
may think the architects are the experts, but you are
the expert in the OR."
Reprinted from OR Manager newsletter,